ODOT release – Crews will be paving and patching areas of Hwy. 101 in Lincoln County over the next two months to fix areas of rough road and improve safety. Travelers should expect crews to be in an area one to three days to complete the work. Plan for lane closures and up to 20 minute delays. Work begins August 8 and is scheduled to be completed by the end of September. All schedules are subject to change and are weather dependent.  The locations are as follows: Aug 22, U.S. 101 north of Lincoln City, milepost 112.5 (night work); Aug 23, U.S. 101, Beverly Beach, milepost 135 (night work); Aug 30, U.S. 101, Waldport to Yachats, milepost 156 -163; Sept 17-19, U.S. 101, Lincoln City, milepost 112-117 (night work). For updates on traffic, go to www.TripCheck.com or call 511. Access for pedestrians, including those with disabilities, is available and identified through or around work zones.

Related Posts